| Project Name: |
Hoboken Ferry Terminal
Rehabilitation - PHASE II |
| Project Address: |
Hoboken, NJ |
| Project Contract Amount: |
$53,877,000.00 |
| Project Executive: |
Mark D. Hall |
| Director of Construction: |
Scott V. Hall |
| Project Manager: |
Conrad F. Hall, Jr. |
| Superintendents: |
Peter von Bradsky & George Bender |
| Owner's Name/Contact Person: |
New Jersey Transit Corp. - Mr.
Jason Wormeck |
| Owner's Address: |
One Penn Plaza East, Newark, NJ |
| Owner's Phone/Fax Numbers: |
Phone: 973-491-8506Fax: 973-491-7024 |
| Construction Mgr./Contact Person: |
Tishman Construction Company - Mr. Randy
Doliber |
| Construction Mgr. Address: |
299 Observer Highway, PO Box 1404, Hoboken,
NJ |
| Construction Mgr. Phone/Fax: |
Phone: 201-222-6400 / Fax: 201-222-3335 |
| Architect's Name: |
Beyer, Binder, Belle Architects & Planners |
| Architect's Address: |
41 East 11th St., New York, NY |
| Architect's Phone Number:
|
Mr. George Beckwith; Phone: (212) 777-7800 |
Description of Project:

|
- Rehabilitation of deteriorated foundations for major transportation
rail/ferry complex
- Drive 26,000 lf of new steel/concrete filled pipe piles
- Re-build deteriorated concrete foundations on six piers
- Replace spalled concrete/extensive spall repairs on six piers
- Complete re-construction of Northwall
- Lead abate structural steel / Asbestos abatement of steam pipe insulation
- Selective Demolition (extensive)
- Re-support column transfer steel
- Construct new steel cribbing
- Construction of new pile caps
- Core drill pilot holes for new piles
- Grout piles
- Extensive excavation and backfilling for foundation work - waterside
- Extensive sub-structure concrete beam and girder repair
- Replace wood and copper facades - entire east elevation (water side)
- Restore structural steel / column re-support
- Install copper roofing and ornamental flashings
- Install new roof drainage system at canopies
- Sandblast all existing steel and re-paint
- Repair all deteriorated steel framing
- Paint all steel elements
- Precast concrete decks throughout all re-built piers
- Monitor & survey construction work for settlement
- Project performed without interruption to Owner's operations
- Work includes coordination with tides/currents since much of the
work is performed under the structure, in the water
- Rebuild new fender racks
- Extensive dredging
- Extensive Marine demolition
|
| Completion Date: |
April 2008 |
| |
|